Solar Installed but Still Dark? Illinois Gives Your Utility 15 Business Days
If your solar panels are installed but still dark in Illinois, the clock that matters is the utility's: under state rule 83 Ill. Adm. Code Part 466, your utility has 7 business days to confirm your Level 1 application is complete and 15 business days to screen it, and Ameren Illinois' own guide says Level 1 witness tests are completed within 15 business days of your installer reporting construction complete, with permanent permission to operate typically two business days after a passed test. Most home systems that stall are stuck on paperwork nobody filed, not on the utility.
The panels went up three weeks ago. The truck is gone, the roof looks finished, and the electric bill that showed up Tuesday is identical to last month's. I get this call more than almost any other — usually from somewhere around Springfield, Edwardsville, or Decatur — and the voice on the other end sits somewhere between confused and furious.
Here's the part that rarely gets explained at the kitchen table. Installing a solar system and being allowed to run it are two separate events, and a state process with real deadlines sits between them.
| Step | Deadline | Source |
|---|---|---|
| Utility tells you whether your application is complete | 7 business days after receipt | 83 Ill. Adm. Code 466.90(b)(2) |
| You supply any missing information | 10 business days, or the request is deemed withdrawn | 466.90(b)(2) |
| Utility verifies the Level 1 screens | 15 business days after the request is complete | 466.90(b)(3) |
| Interconnection agreement (minor modifications needed) | 10 business days after you elect to proceed and pay | 466.90(b)(4)(B) |
| Interconnection agreement (more than minor modifications) | 15 business days after election and payment | 466.90(b)(4)(C) |
| You sign and return the agreement | 30 business days (one 15-day extension allowed) | 466.90(b)(5) |
| Ameren Level 1 witness test | Completed within 15 business days of construction-complete paperwork | Ameren DER guide, effective 6-21-2023 |
| Witness test results | Within 48 hours of the test | Ameren DER guide |
| Permanent permission to operate | Typically within two business days of a passed test | Ameren DER guide |
| Retest after a failed witness test | Scheduled within 30 business days | Ameren DER guide |
| Level 1 application fee (Ameren) | $50 | Ameren DER guide |
Your panels aren't yours to switch on yet
Ameren Illinois publishes a public-facing guide to how it connects distributed energy resources, and the flow chart in it is refreshingly plain. Seven steps: submit application and payment, verify application completeness, engineering review or study, generate and process the interconnection agreement including construction payment, customer and Ameren construction, witness test, grant permission to operate.
Your installer's work — the panels, the racking, the inverter — is step five. Two steps come after it.
The last one has a name worth knowing. Ameren defines permission to operate, or PTO, as "official permission granted by Ameren Illinois to operate DER in parallel of the Ameren Illinois EPS after successfully completing a witness test." Until that letter exists, a finished array is roof decoration.
The state rule nobody hands you
Illinois governs this under 83 Ill. Adm. Code Part 466, the rule covering electric interconnection of distributed energy resources facilities. The current version took effect May 26, 2022, and it applies to systems of 10 MVA or less that aren't under FERC or RTO jurisdiction. Your house is comfortably inside that.
Part 466 sorts projects into four review levels, and home solar almost always lands in Level 1 — the fast lane. A project qualifies for Level 1 if it's inverter-based with lab-certified equipment, has an export capacity of 25 kW or less and a nameplate capacity of 50 kW or less. If the export capacity isn't limited, nameplate can't top 25 kW. A normal Bloomington rooftop at 8 or 10 kW clears that easily.
Level 1 is where the deadlines live:
- 7 business days for the utility to tell you whether your application is complete.
- 15 business days after that for the utility to verify your system passes the Level 1 screens.
- If no utility construction is needed, the conditional agreement to interconnect comes with those screen results. If only minor system modifications are needed, the utility has 10 business days after you elect to proceed and pay the fee to send the interconnection agreement, or 15 if more than minor modifications are needed.
Stack the utility's deadlines and a Level 1 project needing minor modifications runs about 32 business days — call it six and a half weeks — as the outside edge of the paperwork under the rule. With no construction at all, it's 22. Not a promise that it takes that long. A ceiling.
The clock runs both directions, which people forget. You get 10 business days to supply missing information before the request is treated as withdrawn, and 30 business days to sign and return the agreement, with one 15-business-day extension the utility can't refuse. Miss those and you start over. I've watched a homeowner lose five weeks to an unopened envelope.
What Ameren puts in writing
This is where the guide earns its keep, because Ameren commits to numbers most homeowners assume don't exist.
Level 1 costs $50 to apply. Every interconnection gets witness tested — Ameren is explicit that this includes Level 1 facilities, no exceptions. The test is scheduled when your installer submits documentation that construction is complete, and the guide states that "Level 1 witness tests are completed within 15 business days as a technician becomes available to complete the test."
Then it gets faster. Witness test results go to the customer within 48 hours. If everything passes and no power quality meter was used, you get a written conditional permission to operate on the spot, and the guide says a permanent PTO is "typically within two business days of the witness test."
If the test doesn't pass, another one gets scheduled within 30 business days so you have time to fix the problem.
My honest read: that's a tighter set of commitments than the industry's reputation would suggest. When a project drags in Ameren territory, the delay is more often a permit, a corrected application, or an installer who hasn't filed the completion paperwork than it is the utility sitting on a file.
Northern Illinois works the same way in shape. ComEd runs its version through Green Power Connection, and its net metering FAQ says participation begins after your interconnection application is approved and ComEd signs a Certificate of Completion confirming the system has permission to operate. Same two gates: an approval, then a completion sign-off.
The horror stories you found are about a different line
Search this topic for ten minutes and you'll hit an alarming one. In late 2025, news coverage described Ameren Illinois' interconnection queue as backed up for years, with the utility studying large projects one at a time while ComEd reviewed proposals concurrently.
That backlog is real. It is also almost entirely community solar and large distributed projects — not houses.
Ameren's own guide draws the line: Level 1 and smaller Level 2 applications are queued based on when the application was submitted and which circuit will serve it. Larger projects get routed to an engineer to screen aggregate impacts on the sub-transmission system. Different path, different timeline.
If someone quotes you a multi-year wait for a home system in Illinois, they've read the wrong queue. That single confusion has talked more Illinois homeowners out of running the numbers than any objection I hear about price.
Don't let anyone flip it early
Sometimes an installer finishes on a Friday and the homeowner asks the obvious question: can't we just turn it on?
Don't.
The witness test simulates a utility outage to confirm your inverter stops producing instead of quietly energizing a line that crews believe is dead. Ameren's guide is direct that an unintentional island can put energized equipment at ground level within reach of utility personnel and the public. There are also failure modes — a step-up or step-down transformer between the connection point and the inverter, for instance — that can stop a certified inverter from detecting an outage at all, and that only surface during an on-site test.
There's a paperwork reason too. During the test, Ameren personnel verify the installed system matches what was described in the application. And if a power quality meter is used, Ameren's witness test criteria say the disconnect switch stays open until the power quality data is analyzed and a permanent PTO is issued.
Wait for the letter.
Your PTO date is worth money
One more reason to care about this timeline: the date your system was completed and documented sets your net metering terms.
Customers whose systems were installed and fully documented by December 31, 2024 kept full retail rate net metering for what Ameren describes as the 30-year life of the generator, with credits offsetting charges across the whole bill. Systems completed on or after January 1, 2025 get credits on the supply and transmission portions only — delivery charges stay on your bill for every kilowatt-hour you pull, regardless of how much you send back. With Ameren's summer supply price at 11.326¢/kWh for the first 800 kWh and ComEd's at 10.399¢/kWh through September 30, 2026, the supply side is the piece solar is working against.
That's not a reason to rush. It's a reason to understand what you're actually buying before the first payment shows up. I'd rather a customer in Peoria go in with the right expectation than get a pleasant surprise on the sales call and an unpleasant one in July.
Four questions worth asking before you sign
- Which review level did you file, and on what date? Level 1 should be the answer for a house. The submission date sets your place in the queue.
- Who submits the completion paperwork, and how fast after the install? The witness test can't be scheduled until it lands. This is the step that quietly eats weeks.
- What's your plan if the witness test doesn't pass? There's a 30-business-day window to fix problems. A good company already knows that.
- Will you send me the PTO letter itself? Not a text saying you're all set. The document.
An installer who can answer those without checking has done this in Illinois before. One who can't is learning on your roof — and when a solar company folds mid-project, the unfiled completion paperwork is what strands the homeowner.
Where a lease changes the picture
None of the process above changes based on how you pay. Part 466 doesn't care whether you own the panels. What changes is who chases the paperwork.
On a lease, the company that owns the system carries the interconnection filing, the completion documentation, and the follow-up when a witness test gets rescheduled — because it doesn't get paid until the system runs. That alignment is worth more than it sounds. On a cash purchase, which is the path that opens up the state's REC payments, you're more often the one making the phone calls.
A solar lease in Illinois gives you a predictable rate as low as $0.10/kWh for the power your roof produces, with the full 25-year rate schedule set in your contract before you sign. Any savings figure is an estimate until we've looked at your actual usage, your roof, and your utility.
If your panels are up and nothing has happened, call me at (618) 217-2001 or reach out through the contact page. Tell me your install date and which utility you're on, and I can usually tell you within a few minutes which step you're stuck on. Half the time it's a completion form nobody filed. If you're still deciding, the cost breakdown is the honest place to start.
Sources
- 83 Ill. Adm. Code Part 466, Electric Interconnection of Distributed Energy Resources Facilities (Sections 466.10, 466.80, 466.90; amended effective May 26, 2022): https://www.ilga.gov/agencies/JCAR/EntirePart?titlepart=08300466
- Ameren Illinois, Distributed Energy Resources Interconnection Policy Public Facing Guide (effective June 21, 2023): https://www.ameren.com/-/media/illinois-site/files/electricchoice/aic-der-interconnection-policy-public-facing-guide.ashx
- Ameren Illinois, DER Witness Test Criteria (Rev 5, effective January 3, 2023): https://www.ameren.com/-/media/files/account/service-options/renewables/illinois/resources/der-witness-test-criteria.ashx
- Ameren Illinois, Changes to Illinois' Net Metering Program (partner letter, 2024): https://www.ameren.com/-/media/illinois-site/files/electricchoice/changes-to-aic-net-metering.ashx
- ComEd, Green Power Connection Net Metering FAQ (NMR1225, 2026): https://www.comed.com/cdn/assets/v3/assets/blt3ebb3fed6084be2a/bltceb8d9495434223b/695be67c33699162b6ea350c/20065_Net_Metering_FAQ_2025_1223A.pdf
- Plug In Illinois, Ameren Illinois Price to Compare (June 1–September 30, 2026): https://plugin.illinois.gov/understanding-the-price-to-compare/price-to-compare-ameren-illinois.html
- Plug In Illinois, ComEd Price to Compare (June 1–September 30, 2026): https://plugin.illinois.gov/understanding-the-price-to-compare/price-to-compare-comed.html
Timelines above are the deadlines those documents set, not a prediction of any individual project. Every project is different — I'm a registered Designee under Illinois Shines, not your utility.