Will Your Illinois Electric Bill Go Back Down? PJM Just Locked In Prices Through 2029
Short answer: not soon. On July 14, 2026, PJM announced that its capacity auction for the 2028-29 delivery year cleared at $325 per megawatt-day — the third auction in a row to clear at the FERC-approved price cap. That means the capacity piece of a ComEd bill is set at that level through May 31, 2029.
I've been telling customers for two years that Illinois electric rates went up because of a "spike." I need to correct myself. It's not a spike anymore. It's a plateau — and we now know it holds through at least May 2029.
PJM is the grid operator for northern Illinois and ComEd. Its newest result is the clearest answer yet to the question I get more than any other: when does my bill go back down?
The "spike" people keep waiting to reverse
When a price jumps, most of us assume it'll ease back. That's the instinct I hear on every call — "I'll wait for rates to settle before I do anything about solar."
Here's what the auction results actually look like (PJM Base Residual Auction clearing prices, RTO-wide):
| PJM delivery year | Capacity price ($/MW-day) | Auction result announced |
|---|---|---|
| 2024-25 | $28.92 | — |
| 2025-26 | $269.92 | — |
| 2026-27 | $329.17 (price cap) | July 22, 2025 |
| 2027-28 | $333.44 (price cap) | Dec. 17, 2025 |
| 2028-29 (new) | $325.00 (price cap) | July 14, 2026 |
Look at that column. The jump from $28.92 to $269.92 was the shock everyone felt on their 2025 and 2026 bills. But the three years after it don't come back down — they sit in a band around $325 to $333. The market didn't correct. It found a new, much higher floor. And PJM's own report says that without the cap, the 2028-29 price would have been far higher still.
That matters because capacity is set at auction years in advance. The 2028-29 number was decided in July, in a bidding window that ran June 30 through July 7, 2026. It's already locked. Nobody's waiting on a future event to find out where that piece of the bill lands — it landed.
What a "capacity price" even is
Quick version, because it's easy to glaze over. Capacity is the grid paying power plants to promise they'll show up on the hottest, highest-demand days. ComEd sits inside PJM, so whatever PJM's auction clears at gets passed to ComEd customers as a capacity charge.
Citizens Utility Board pegs capacity costs at roughly 20 percent of the price ComEd customers pay for electricity — and it's the fastest-growing piece. CUB also notes ComEd customers are now paying a power price about 50 percent higher than two years ago.
Why did it climb? Mostly data centers. They're adding enormous new demand, the auction has to secure more supply to cover it, and the price rises for everyone. I did a full breakdown of that in my data centers and your electric bill piece — start there if you want the mechanism and the numbers behind the buildout. For this post, the point is narrower: the newest auction confirms the trend isn't reversing.
So when does my bill go back down?
For the capacity piece, the honest answer is: not through the 2028-29 delivery year, because it's already priced. Your supply and delivery charges will still wiggle around — supply resets every June 1 and October 1, delivery depends on pending rate cases — but the part that's been driving the increases is committed at a high level for years out.
Downstate isn't off the hook either. Central and southern Illinois run on MISO, not PJM, and MISO's own capacity price spiked hard — its summer 2025 price cleared at $666.50 per megawatt-day in the 2025-26 auction. Ameren Illinois passes that straight through, same as ComEd does up north, and Ameren's next multi-year delivery rate plan, covering 2028 through 2031, is due to be filed in 2027. Its summer supply price sits at 11.326 cents per kilowatt-hour through September 30, 2026, which puts the estimated all-in summer rate near 19 cents. My Ameren bill and MISO post walks through that side in detail.
North or south, it's the same shape: capacity-driven costs, set in advance, with no relief on the calendar.
What's being done about it
I don't want to leave you thinking nobody's fighting this. Plenty of people are.
CUB is pushing three specific reforms off this latest auction: PJM should require data centers that don't bring their own new power to be interruptible on peak days; Illinois should pass the state POWER Act, which would make data centers pay their own interconnection costs and bring new capacity instead of leaning on residential customers; and Congress should pass the federal Power for the People Act. Governor Pritzker also directed the state to pause new Data Center Investment Program tax-incentive agreements starting July 1, 2026.
Those are real steps, and I hope they land. But I'll be straight with you: none of them un-price an auction that already cleared. The 2026-27, 2027-28, and 2028-29 capacity costs are set. Even a good reform passed this year mostly protects the auctions that haven't happened yet.
That's the piece I want you to sit with. Waiting for policy to lower the bill you're paying now is a long bet on a slow process.
The part you actually control
You can't vote in a capacity auction. You can't stop the next data center in Joliet or DeKalb. But you can decide what rate you pay for the power your own roof makes.
A solar lease in Illinois can start at a predictable rate as low as 10 cents per kilowatt-hour for the 25-year term — the full rate schedule is set in your contract before you sign. Compare that with this summer's estimated all-in rates of roughly 17 cents for ComEd and 19 cents for Ameren. That number doesn't care what PJM clears at in 2028. You know your number for 25 years because the schedule is in your contract.
For income-qualified households, Solar for All offers "guaranteed savings with no solar payment & reduced utility bills" — that's the program's own language, not a claim I'm making. And if outages worry you as much as cost, a battery paired with Illinois's $300-per-kWh utility battery rebate keeps your fridge and sump pump running when the grid strains — which, given the reliability warnings tied to this same demand growth, is worth a look.
I'm a local installer with trusted Illinois partners, so I can show you lease, cash, and Solar for All side by side and let the numbers decide. Run yours on the Solar Savings Calculator, look up current ComEd and Ameren rates, or just call me at (618) 217-2001.
The auction already told us where rates are headed through 2029. The only open question is whether you're along for that ride or you already know your own number.
Sources
- PJM news release, 2028/2029 Base Residual Auction results (July 14, 2026)
- PJM 2028/2029 Base Residual Auction Report (July 14, 2026)
- PJM Inside Lines: 2028/2029 auction bidding window opens (June 30, 2026)
- PJM news release, 2027/2028 Base Residual Auction results (Dec. 17, 2025)
- Citizens Utility Board on the 2028-29 auction and prior prices (July 15, 2026)
- MISO 2025-26 Planning Resource Auction results (April 28, 2025)
- Plug In Illinois: Ameren Illinois Price to Compare (June 1–Sept. 30, 2026)
- Plug In Illinois: ComEd Price to Compare (June 1–Sept. 30, 2026)
- Governor's office: pause on new Data Center Investment Program agreements (June 5, 2026)
- Illinois Solar for All program language